Question: Will's Welded Widgets (WWW) makes its Q Model from components R, S, and T. Component Ris made from 3 units of component X and 3


Will's Welded Widgets (WWW) makes its Q Model from components R, S, and T. Component Ris made from 3 units of component X and 3 unit of component Y. Component T is made from 1 unit of component Vand 2 units of component Z. Using the given information and the beginning inventories 80 units of component T and 200 units of component R, calculate the minimum replenishment time for the 80 Q Models. Q R S Y Z Usage per Parent Lead Time (weeks) Item Q 1 2 R 3 5 S 2 4. T 1 3 3 3 Y 3 4. V 1 4. Z 2. . 5 The cumulative lead time is weeks