Question: With reference to the formula and the table below: Activity Duration=TE a + 4m + b 6 Activity Optimistic Pessimistic Likely Task 1 7 15

 With reference to the formula and the table below: Activity Duration=TE

With reference to the formula and the table below: Activity Duration=TE a + 4m + b 6 Activity Optimistic Pessimistic Likely Task 1 7 15 8 Task 2 4 12 9 Task3 5 22 6 Task 4 2 30 5 Which task would be estimated to be the QUICKEST to complete using the Activity Duration Formula above? Task The Excel spreadsheet can be accessed here. For further information see Spacer