Question: With the data shown below (IP-Immediate Predecessor; NT-Normal Time in weeks; CT- Crash Time in weeks), do the following: a. Make a network diagram. b.

With the data shown below (IP-Immediate

With the data shown below (IP-Immediate Predecessor; NT-Normal Time in weeks; CT- Crash Time in weeks), do the following: a. Make a network diagram. b. In a network table, compute the float of each activity. c. Find the critical path. Activity/IP/NT/CT A/ None/4/2 B/ None/2/1 C/ None/3/2 D/A/1/0.5 E/ B/ 5/ 3 F/C/4/3 G/DE/3/2 Hidummy)/B/0/0 1/ FH/6/4 J/G1/2/1 K/ J/5/3 LI J/ 3/2 M/K/4/3 N/L,M/1/1 O/K/4/2 P/N/2/1