Question: Work Management WM1 Preventive maintenance tasks should be grouped by? A. Parts required, task interval and lockout -tag out requirement B. Skill required, parts required

Work Management

WM1

Preventive maintenance tasks should be grouped by?

A. Parts required, task interval and lockout -tag out requirement

B. Skill required, parts required and equipment availability

C. Skill required, task and interval

D. Skill required, task interval and lockout -tag out requirement

WM2

When deciding if you should keep a part in stock, which of the following should be

Your primary concern?

A. Is the equipment it fits on the critical equipment list?

B. Does the manufacturer suggest stocking it?

C. Would plant (facility) output be affected?

D. Is the store's inventory too high?

WM3

In the broadest view, a maintenance planner:

A. places first priority on extensive research to determine possible parts, tools and support

requirements.

B. writes procedures and gathers tools and parts necessary to do a job quickly and reliably.

C. gives the maintenance organization information to allow scheduling and execution of its

work.

D. ensures good control of vendors that are sources of material, tools, and maintenance

Supplies

WM4

A decision is made to accompany the vibration technician on a data collection route. What

Are the most important things the observer should be watching for in the technician's

performance?

A. That measurements are collected in the proper route sequence, allowing for machines

that are shut down or not warmed up.

B. That measurements are recorded on all equipment that is operating on the route,

regardless of sequence.

C. That the technician observes and notes other conditions such as leaks, loose bolts, dirty

oil, failed gages, etc.

D. That measurements are taken in displacement and velocity as well as acceleration units

WM5

Which list of elements below are the most important to be evaluated and coordinated

during the planning phase of a major shutdown of your operating area (i.e. annual

turnaround)?

A. Historical turnaround maintenance days, operations desired work list, prior turnaround

work lists

B. Available turnaround budget, equipment condition, budgeted down-days

C. Condition and remaining life of critical equipment, value of production throughput, labor

and materials availability and cost

D. Heavy lifting equipment availability, labor cost and availability, operations requested

down-days

WM6

The scheduler should assign work plans for the crew to execute what percentage of the

forecasted hours?

A. 100% to fill all available forecasted hours

B. More than 100% in case some jobs do not take as long

C. Less than 100% to allow for emergencies or breaks

D. It does not matter how much is scheduled

WM7

What is the statistical average and the population standard deviation of the following series

of numbers?

1.30, 1.25, 1.50, 1.12, 1.35, 1.38

A. Statistical average = 1.32; standard deviation= 0.128

B. Statistical average = 1.50; standard deviation= 0.25

C. Statistical average = 1.32; standard deviation= 1.50

D. Statistical average = 0.128: standard deviation= 1.32

WM8

When should completed work orders be turned in to the supervisors?

A. at the end of the day

B. at the end of the shift

C. after completing a group of tasks

D. upon completion of the work

WM9

Which one of the following metrics definitions is not accurate?

A. Work Order Cycle Time - average number of hours jobs are planned in advance of

execution

B. Mean TimeTo Repair (MTIR) how long it takes to fix broken equipment

C. Estimated Asset Replacement Value per Mechanic - how much equipment value is

maintained by each mechanic

D. % Planned Work - the amount of completed work that was planned ahead of time

WM9

One way to catch up on back log hours in PM's is to hire outside contractors to complete

backlog work tasks. What should a reliability engineer do when making this decision?

A. assure contractor personnel have many years of experience

B. assure contractors have training programs and documentation from other plant

operations

C. assure contractors have proper safety paperwork on file

D. assure contractors have been trained in work tasks

WM10

The planning function should focus primarily on:

A. Accurate estimates.

B. Material availability.

C. Equipment records.

D. Future work

WM11

For maximum effectiveness maintenance tasks should be allocated to:

A. Operations performing minor maintenance and multiskilled technicians performing

complex maintenance tasks.

B. Operations and/or maintenance depending on availability.

C. Multiskilled maintenance technicians performing all maintenance tasks.

D. A contracted maintenance person to handle all aspects of maintenance

WM12

As the maintenance manager for a manufacturing company, you have conducted a study

that reveals the mechanics, on average, spend four hours per ten hour shift on wrench time

(tool turning time). Your first action should be:

A. Improve planning and scheduling to increase wrench time (tool turning time).

B. Encourage your planners to develop more aggressive job estimates.

C. Inform management that four hours wrench time (tool turning time) per day is

considered good.

D. Investigate the barriers causing loss of wrench time (tool turning time).

WM13

When measuring the temperature of an object using a radiometric imager, which two

parameters have the greatest effect on accuracy of the temperature reading on the

instrument?

A. Relative humidity and ambient air temperature

B. Emissivity and background temperature

C. Aperture and brightness

D. Range and span

WM14

The maintenance manager of a bearing manufacturer has asked you to calculate the

reorder point of a spare part item. She has provided you with the following information to

facilitate your calculations. The cost of the spare parties$100. The cost of earning inventory

is 20% of the cost of the part. The cost of placing an order is$40 for which the annual

demand is 100,000 units. The average tad-time for replenishment is two weeks and the

buffer stock of 500 units S desired and the average inventory is 100 units per week. What

is the reorder point in units for this spare part?

A. 350 units

B. 600 units

C. 700 units

D. 707 units

E. 1200 units

WM15

The two primary costs in the classical inventory management models that are utilized to

determine the Economic Order Quantity (EOQ) are the acquisition cost of inventory and the

inventory possession cost. Which of the following best describes the relationship of these

costs with the number of inventory turns per year as the number of turns per year

increases?

A. acquisition cost increases and inventory possession cost increases

B. inventory possession cost and variable cost increase

C. acquisition cost decreases and inventory possession cost increases

D. acquisition cost increases and inventory possession cost decreases

WM16

On Monday, the maintenance manager sent an e-mail memo to the production manager

saying that the date and time of the next planned outage would be on the third shift of the

coming Friday. When the maintenance manager arrived at the unit on Friday third shift, the

equipment was still operating at full capacity. The operator said he knew nothing of a

planned outage and he had to make up production on this shift. Which of the following is

the most likely reason the equipment was still running?

A. The maintenance manager did not know if the production manager had communicated

the plan to the shift leader.

B. The maintenance manager did not know if the production manager received his e-mail

communication.

C. The maintenance manager made a unilateral decision it was time to do the outage.

D. The maintenance manager did not know if the production schedule allowed for the

planned downtime

WM17

Grouping of data into families and eliminating statistical outliers from a statistical alarm

calculation:

A. Is not necessary as the standard deviation process corrects for all deviations.

B. Must be performed to assure proper calculation of statistical alarms.

C. Will only affect the bad data, but not affect the good data.

D. Can be dealt with by using the percent offset method.

WM18

You are new to the job of maintenance manager. As you start reviewing the work done by

your five planners you find that, on average, they are dividing their time as follows:

5% Interviewing area personnel to scope out jobs

2% Creating pipe sketches and other small drawings

9% Ordering materials through the Computerized Maintenance Management System

(CMMS)

5% Creating work order estimates

15% Researching what spare parts are needed and where to find them

25% Expediting materials that have not come in yet

5% Creating material kits for future jobs and maintaining the kitting area

1% Creating formal job steps in the work order record in the CMMS

10% Checking on field progress of the larger jobs

15% Talking with mechanics to explain the details of work they are to perform

8% Closing work orders and other data clean up tasks in the CMMS

In which two areas should you concentrate onto make the planners more productive?

A. Eliminate the practice of job materials kitting or staging and purchase a different

computerized maintenance and materials system

B. Encourage the planners to create more detailed job instructions in the work order record

and hire another designer draftsman

C. Increase the planning horizon and improve the quality of bills of material in the

computerized maintenance and materials system

D. Improve their communication skills through training and train all planners on proper

estimation methods

WM 19

Motor Circuit Analysis (MCrA) on a low (450-600) voltage 3 Phase motor reveals

significantly higher capacitance-to-ground than baseline values. Resistance-to-ground

readings are good. What does this indicate and/or what should you do?

A. The motor contains abnormally high moisture and/or conductive contamination. Continue

normal operation, but plan follow-on MCrA readings and possible corrective action.

B. Remove motor-from service and send to shop to be cleaned, dried, dipped and baked,

since this is the surest way to corrective problem.

C. Do not start the motor. An "explosive" shorting condition could cause near instantaneous

winding failure.

D. No problem exists. Take no action.

WM20

Determining the optimal replacement time for spares (spare parts) with an unacceptable

interval, needs to account for:

A. The depreciated value of the equipment.

B. The value of money changing over time.

C. The interest charges for capital expenditures.

D. The cost of borrowing versus interest lost on operating funds

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!