Question: Work Management WM1 Preventive maintenance tasks should be grouped by? A. Parts required, task interval and lockout -tag out requirement B. Skill required, parts required
Work Management
WM1
Preventive maintenance tasks should be grouped by?
A. Parts required, task interval and lockout -tag out requirement
B. Skill required, parts required and equipment availability
C. Skill required, task and interval
D. Skill required, task interval and lockout -tag out requirement
WM2
When deciding if you should keep a part in stock, which of the following should be
Your primary concern?
A. Is the equipment it fits on the critical equipment list?
B. Does the manufacturer suggest stocking it?
C. Would plant (facility) output be affected?
D. Is the store's inventory too high?
WM3
In the broadest view, a maintenance planner:
A. places first priority on extensive research to determine possible parts, tools and support
requirements.
B. writes procedures and gathers tools and parts necessary to do a job quickly and reliably.
C. gives the maintenance organization information to allow scheduling and execution of its
work.
D. ensures good control of vendors that are sources of material, tools, and maintenance
Supplies
WM4
A decision is made to accompany the vibration technician on a data collection route. What
Are the most important things the observer should be watching for in the technician's
performance?
A. That measurements are collected in the proper route sequence, allowing for machines
that are shut down or not warmed up.
B. That measurements are recorded on all equipment that is operating on the route,
regardless of sequence.
C. That the technician observes and notes other conditions such as leaks, loose bolts, dirty
oil, failed gages, etc.
D. That measurements are taken in displacement and velocity as well as acceleration units
WM5
Which list of elements below are the most important to be evaluated and coordinated
during the planning phase of a major shutdown of your operating area (i.e. annual
turnaround)?
A. Historical turnaround maintenance days, operations desired work list, prior turnaround
work lists
B. Available turnaround budget, equipment condition, budgeted down-days
C. Condition and remaining life of critical equipment, value of production throughput, labor
and materials availability and cost
D. Heavy lifting equipment availability, labor cost and availability, operations requested
down-days
WM6
The scheduler should assign work plans for the crew to execute what percentage of the
forecasted hours?
A. 100% to fill all available forecasted hours
B. More than 100% in case some jobs do not take as long
C. Less than 100% to allow for emergencies or breaks
D. It does not matter how much is scheduled
WM7
What is the statistical average and the population standard deviation of the following series
of numbers?
1.30, 1.25, 1.50, 1.12, 1.35, 1.38
A. Statistical average = 1.32; standard deviation= 0.128
B. Statistical average = 1.50; standard deviation= 0.25
C. Statistical average = 1.32; standard deviation= 1.50
D. Statistical average = 0.128: standard deviation= 1.32
WM8
When should completed work orders be turned in to the supervisors?
A. at the end of the day
B. at the end of the shift
C. after completing a group of tasks
D. upon completion of the work
WM9
Which one of the following metrics definitions is not accurate?
A. Work Order Cycle Time - average number of hours jobs are planned in advance of
execution
B. Mean TimeTo Repair (MTIR) how long it takes to fix broken equipment
C. Estimated Asset Replacement Value per Mechanic - how much equipment value is
maintained by each mechanic
D. % Planned Work - the amount of completed work that was planned ahead of time
WM9
One way to catch up on back log hours in PM's is to hire outside contractors to complete
backlog work tasks. What should a reliability engineer do when making this decision?
A. assure contractor personnel have many years of experience
B. assure contractors have training programs and documentation from other plant
operations
C. assure contractors have proper safety paperwork on file
D. assure contractors have been trained in work tasks
WM10
The planning function should focus primarily on:
A. Accurate estimates.
B. Material availability.
C. Equipment records.
D. Future work
WM11
For maximum effectiveness maintenance tasks should be allocated to:
A. Operations performing minor maintenance and multiskilled technicians performing
complex maintenance tasks.
B. Operations and/or maintenance depending on availability.
C. Multiskilled maintenance technicians performing all maintenance tasks.
D. A contracted maintenance person to handle all aspects of maintenance
WM12
As the maintenance manager for a manufacturing company, you have conducted a study
that reveals the mechanics, on average, spend four hours per ten hour shift on wrench time
(tool turning time). Your first action should be:
A. Improve planning and scheduling to increase wrench time (tool turning time).
B. Encourage your planners to develop more aggressive job estimates.
C. Inform management that four hours wrench time (tool turning time) per day is
considered good.
D. Investigate the barriers causing loss of wrench time (tool turning time).
WM13
When measuring the temperature of an object using a radiometric imager, which two
parameters have the greatest effect on accuracy of the temperature reading on the
instrument?
A. Relative humidity and ambient air temperature
B. Emissivity and background temperature
C. Aperture and brightness
D. Range and span
WM14
The maintenance manager of a bearing manufacturer has asked you to calculate the
reorder point of a spare part item. She has provided you with the following information to
facilitate your calculations. The cost of the spare parties$100. The cost of earning inventory
is 20% of the cost of the part. The cost of placing an order is$40 for which the annual
demand is 100,000 units. The average tad-time for replenishment is two weeks and the
buffer stock of 500 units S desired and the average inventory is 100 units per week. What
is the reorder point in units for this spare part?
A. 350 units
B. 600 units
C. 700 units
D. 707 units
E. 1200 units
WM15
The two primary costs in the classical inventory management models that are utilized to
determine the Economic Order Quantity (EOQ) are the acquisition cost of inventory and the
inventory possession cost. Which of the following best describes the relationship of these
costs with the number of inventory turns per year as the number of turns per year
increases?
A. acquisition cost increases and inventory possession cost increases
B. inventory possession cost and variable cost increase
C. acquisition cost decreases and inventory possession cost increases
D. acquisition cost increases and inventory possession cost decreases
WM16
On Monday, the maintenance manager sent an e-mail memo to the production manager
saying that the date and time of the next planned outage would be on the third shift of the
coming Friday. When the maintenance manager arrived at the unit on Friday third shift, the
equipment was still operating at full capacity. The operator said he knew nothing of a
planned outage and he had to make up production on this shift. Which of the following is
the most likely reason the equipment was still running?
A. The maintenance manager did not know if the production manager had communicated
the plan to the shift leader.
B. The maintenance manager did not know if the production manager received his e-mail
communication.
C. The maintenance manager made a unilateral decision it was time to do the outage.
D. The maintenance manager did not know if the production schedule allowed for the
planned downtime
WM17
Grouping of data into families and eliminating statistical outliers from a statistical alarm
calculation:
A. Is not necessary as the standard deviation process corrects for all deviations.
B. Must be performed to assure proper calculation of statistical alarms.
C. Will only affect the bad data, but not affect the good data.
D. Can be dealt with by using the percent offset method.
WM18
You are new to the job of maintenance manager. As you start reviewing the work done by
your five planners you find that, on average, they are dividing their time as follows:
5% Interviewing area personnel to scope out jobs
2% Creating pipe sketches and other small drawings
9% Ordering materials through the Computerized Maintenance Management System
(CMMS)
5% Creating work order estimates
15% Researching what spare parts are needed and where to find them
25% Expediting materials that have not come in yet
5% Creating material kits for future jobs and maintaining the kitting area
1% Creating formal job steps in the work order record in the CMMS
10% Checking on field progress of the larger jobs
15% Talking with mechanics to explain the details of work they are to perform
8% Closing work orders and other data clean up tasks in the CMMS
In which two areas should you concentrate onto make the planners more productive?
A. Eliminate the practice of job materials kitting or staging and purchase a different
computerized maintenance and materials system
B. Encourage the planners to create more detailed job instructions in the work order record
and hire another designer draftsman
C. Increase the planning horizon and improve the quality of bills of material in the
computerized maintenance and materials system
D. Improve their communication skills through training and train all planners on proper
estimation methods
WM 19
Motor Circuit Analysis (MCrA) on a low (450-600) voltage 3 Phase motor reveals
significantly higher capacitance-to-ground than baseline values. Resistance-to-ground
readings are good. What does this indicate and/or what should you do?
A. The motor contains abnormally high moisture and/or conductive contamination. Continue
normal operation, but plan follow-on MCrA readings and possible corrective action.
B. Remove motor-from service and send to shop to be cleaned, dried, dipped and baked,
since this is the surest way to corrective problem.
C. Do not start the motor. An "explosive" shorting condition could cause near instantaneous
winding failure.
D. No problem exists. Take no action.
WM20
Determining the optimal replacement time for spares (spare parts) with an unacceptable
interval, needs to account for:
A. The depreciated value of the equipment.
B. The value of money changing over time.
C. The interest charges for capital expenditures.
D. The cost of borrowing versus interest lost on operating funds
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
