Question: WORK ON THE EXERCISE. 1 Project Speedy 1 point The value of salvaged fixed asset at the final year of the project is RM Project

WORK ON THE EXERCISE. 1 Project Speedy 1 point The value of salvaged fixed asset at the final year of the project is RM Project Speedy Type your answer... Details 40% is fixed assets' cost that 60% can be salvaged a the end of the project Project cost 1,500,000.00 2 Operating Cash Flows 1 point Terminal Value of the project is RM Type your answer... 1 600,000.00 2 750,000.00 3 500,000.00 4 300,000.00 5 300,000.00 6 300,000.00 5.83% 3 1 point PV of the OCF in Year 1 is RM Cost of capital Type your answer... 4 1 point PV of the OCF in Year 4 is RM Type your answer... 5 1 point Total PV is RM Type your