Question: Work should be released into the system when: A) a customer order is received. B) the first step in the process is idle. C) a
Work should be released into the system when:
|
|
|
| A) | a customer order is received. |
|
|
|
| B) | the first step in the process is idle. |
|
|
|
| C) | a customer order is completed. |
|
|
|
| D) | the bottlenecks need work. |