Question: According to the Drum Buffer Rope system, new work should be released into the system when: the bottlenecks need work. a customer order is received.
According to the Drum Buffer Rope system, new work should be released into the system when:
the bottlenecks need work.
a customer order is received.
a customer order is completed.
the first step in the process is idle.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock