Question: You are a Program Manager at Gagglezon Software and responsible for the project represented in the table below. You and your team have made estimates
You are a
Program Manager
at
Gagglezon Software
and responsible for the project represented in the table below. You and your team have made estimates for "optimistic", "most likely", and "pessemistic" task durations. You have determined that the critical path is A-D-E.
Gagglezon Software
| Activity | Optimistic Time | Most Likey Time | Pessimistic Time |
| A | 3 days | 7 days | 15 days |
| B | 4 days | 8 days | 12 days |
| C | 6 days | 8 days | 10 days |
| D | 2 days | 4 days | 8 days |
| E | 8 days | 14 days | 20 days |
Using PERT analysis - what is the duration of the project based on expected times?
enter your response here
days (round to one decimal place)
What is the project variance?
enter your response here
days (round to the nearest one decimal place)
Your boss at
Gagglezon Software
requires that the project be done in
28
days. How likely are you to complete the project within the required duration?
Step by Step Solution
There are 3 Steps involved in it