Question: You are a Program Manager at Gagglezon Software and responsible for the project represented in the table below. You and your team have made estimates

You are a

Program Manager

at

Gagglezon Software

and responsible for the project represented in the table below. You and your team have made estimates for "optimistic", "most likely", and "pessemistic" task durations. You have determined that the critical path is A-D-E.

Gagglezon Software

Activity

Optimistic Time

Most Likey Time

Pessimistic Time

A

3

days

7

days

15

days

B

4

days

8

days

12

days

C

6

days

8

days

10

days

D

2

days

4

days

8

days

E

8

days

14

days

20

days

Using PERT analysis - what is the duration of the project based on expected times?

enter your response here

days (round to one decimal place)

What is the project variance?

enter your response here

days (round to the nearest one decimal place)

Your boss at

Gagglezon Software

requires that the project be done in

28

days. How likely are you to complete the project within the required duration?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!