Question: You are building a deck that has the associated tasks and activities below. Your project team consists of a Foreman, Carpenter, Backhoe Operator and General

  1. You are building a deck that has the associated tasks and activities below. Your project team consists of a Foreman, Carpenter, Backhoe Operator and General Laborer.
    1. Develop a WBS for the project
    2. Develop a RAM for the project
    3. Develop an OBS for the project

BUILD DECK

  • Site Preparation Clear Site Remove Debris
  • Purchase Material Estimate Quantities Purchase Lumber Purchase Tools
  • Construct Deck Dig Footings Build Frame Lay Decking Seal Lumber
  • Clean Up Return unused Materials Remove Scrap