Question: You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): LOADING... . a. What are
You are choosing between two projects. The cash flows for the projects are given in the following table ($ million):
LOADING...
.
a. What are the IRRs of the two projects?
b. If your discount rate is
5.2%,
what are the
NPVs
of the two projects?
c. Why do IRR and NPV rank the two projects differently?
Project Year 0 Year 1 Year 2 Year 3 Year 4 A -51 27 20 19 13 B -99 19 39 51 61