Question: You are choosing between two projects. The cash flows for the projects are given in the following table (S million): Project Year 3 Year 0

You are choosing between two projects. The cash flows for the projects are given in the following table (S million): Project Year 3 Year 0 551 Year 1 Year 2 $19 538 Year 4 512 561 527 $102$22 $50 a. What are the IRRs of the two projects? b. If your discount rate is 4 9%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently