Question: You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project Year 0 Year 1
You are choosing between two projects. The cash flows for the projects are given in the following table ($ million):
| Project | Year 0 | Year 1 | Year 2 | Year 3 | Year 4 |
| A | $49 | $26 | $18 | $20 | $16 |
| B | $99 | $22 | $42 | $48 | $62 |
a. What are the IRRs of the two projects?
b. If your discount rate is 5.1%, what are the NPVs of the two projects?
c. Why do IRR and NPV rank the two projects differently?