Question: You are considering two mutually exclusive projects with the following cash flows. Which project(s) should you accept if the discount rate is 8.5 percent? What
You are considering two mutually exclusive projects with the following cash flows. Which project(s) should you accept if the discount rate is 8.5 percent? What if the discount rate is 13 percent?
| Year | Project A | Project B |
| 0 | -$80,000 | -$80,000 |
| 1 | 31,000 | 0 |
| 2 | 31,000 | 0 |
| 3 | 31,000 | 0 |
A.) accept A at 8.5 percent and B at 13 percent
B.) accept B at 8.5 percent and A at 13 percent
C.) Accept B at 8.5% and neither at 13 percent
D.) accept A at 8.5 percent and neither at 13 percent
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
