Question: You are considering two mutually exclusive projects with the following cash flows. Which project(s) should you accept if the discount rate is 8.5 percent? What
You are considering two mutually exclusive projects with the following cash flows. Which project(s) should you accept if the discount rate is 8.5 percent? What if the discount rate is 13 percent?
Year 0 1 2 3
Project A -80,000 31,000 31,000 31,000
Project B -80,000 0 0 110,000