Question: You are constructing 8 additional rooms to an office building. Each room is identical and the projected costs for the project are $160,000 and construction
You are constructing 8 additional rooms to an office building. Each room is identical and the projected costs for the project are $160,000 and construction is expected to take 8 weeks.
At the end of week 3, you have spent $22,000 per room and you have finished 2 rooms.
Based on the information provided above, calculate the values for the items below.
| Value | |
| Budget At Completion |
|
| Planned Value |
|
| Earned Value | |
| Actual Cost | |
| Cost Variance | |
| Schedule Variance | |
| Cost Performance Index | |
| Schedule Performance Index | |
| Estimated At Completion | |
| Estimated To Completion | |
| Variance At Completion | |
| To-Complete Performance Index (Cost) |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock