Question: You are developing a performance progress report for a project you are managing. The following time-phased budget was developed earlier in the planning stage and
You are developing a performance progress report for a project you are managing. The following time-phased budget was developed earlier in the planning stage and is being used as the standard against which the project performance is measured. At the end of Week 6 , Activity " B " is 90% complete and its actual cost is 15 . What is the Planned Value of this activity? Use two decimal places in your calculations