Question: You are developing a performance progress report for a project time - phased budget was developed earlier in the planning stage and is being used

You are developing a performance progress report for a project time-phased budget was developed earlier in the planning stage and is being used as the standard against which the project performance is measured.
\table[[Work Packages,W1,W2,W3,W4,W5,W6,W7,W8,W9,W10,W11],[A,3,6,6,,,,,,,,],[B,,,,3,3,2,,,,,],[C,,,,,,,4,5,6,3,5],[Total,3,6,6,3,3,2,4,5,6,3,5]]
You are analyzing the project performance at the end of Week 8. Activity "C" is 20% complete and its actual cost is 2. What is the Cost Performance Index of this activity?
Use two decimal places in your calculations.
 You are developing a performance progress report for a project time-phased

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!