Question: You are developing a performance progress report for a project you are managing. The following time-phased budget was developed earlier in the planning stage and

You are developing a performance progress report
You are developing a performance progress report for a project you are managing. The following time-phased budget was developed earlier in the planning stage and is being used as the standard against which the project performance is measured. You are analyzing the project performance at the end of Week 5. Activity "C" is 80% complete and its actual cost is 15 . What is the schedule variance of this activity? Use two decimal places in your calculations

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts