Question: You are developing a performance progress report for a project you are managing. The following time-phased budget was developed earlier in the planning stage and

You are developing a performance progress report
You are developing a performance progress report for a project you are managing. The following time-phased budget was developed earlier in the planning stage and is being used as the standard against which the project performance is measured. At the end of Week 8 , activity " C " is 50% complete. What is the Earned Value of this activity? Use two decimal places in your calculations