You are developing a performance progress report for a project you are managing. The following time-phased budget was developed earlier in the planning stage and is being used as the standard against which the project performance is measured.
|
|
You are analyzing the project performance at the end of Week 2. Activity "A" is 50% complete and its actual cost is 5. What is the cost variance of this activity?
Use two decimal places in your calculations.