Question: You are evaluating two projects. You may accept only one of them. Project one will cost $379,000 initially and will pay $134,000 each year for
You are evaluating two projects. You may accept only one of them. Project one will cost $379,000 initially and will pay $134,000 each year for the next 5 years. Project two will cost $454,000 initially, but will pay $101,000 for the next 10 years. The firm's cost of capital is 15%. Use the replacement chain approach to compute the NPV of each project. Which project has the highest NPV and by how much? Round your answers to the nearest dollar.