Question: You are faced with a task for designing and manufacturing a new product. Table 8.1 shows a set of tasks, their predecessors, and optimistic, most

You are faced with a task for designing and manufacturing a new product. Table 8.1 shows a set of tasks, their predecessors, and optimistic, most likely, and pessimistic durations for each activity involved in the production of this new product. Table 8.1 Important activities for the development of a new product 1. Determine the critical path, using the expected activity times. Blank 1 2. What is the probability of completing the project within week 50 ? Blank 2
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
