Question: You are given the following data to construct a aggregate plan. Cost data Regular time labor cost per unit RM 10 Overtime time labor cost
You are given the following data to construct a aggregate plan.
Cost data
Regular time labor cost per unit RM 10
Overtime time labor cost per hour RM 15
Subcontracting cost per unit (labor only) RM 80
Back order cost per unit per period RM 20
Inventory holding cost per unit per period RM 10
Hiring cost per employee RM 500
Firing cost per employee RM 400
Capacity Data
Beginning workforce 40 employees
Beginning inventory 500 units
Beginning back orders 0 units
Regular production available per period (unit) 100 units per period per worker
Quarter Demand
1 4,420
2 2,480
3 2,200
4 3,280
(a) What is the required workforce level and how many worker(s) are hired or fired at the beginning of period 1? What is the total cost involved for the strategy.
(b) Develop a matching demand (chase) aggregate plan. Compute the total cost involved for the strategy.
(c) Which aggregate plan is better off?
(d) If the manufacturer is practicing matching demand for its aggregate plan, calculate the material cost for second period if
(i) 5 units of product require 1 unit of material and the material cost is RM20 per unit.
(ii) 1 unit of product require 2 units of material and the material cost is RM50
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts