Question: You are given the following earned value analysis information for a 10-month project at the end of the 7th month: SPI = 0.7, CPI =
You are given the following earned value analysis information for a 10-month project at the end of the 7th month: SPI = 0.7, CPI = 1.0. Which of the following choices best describes the information provided?
| The project's deliverables have all been finished. The project came in on schedule but over budget. | ||
| The project is behind schedule but underspending its budget. | ||
| At that time the project was behind schedule and on budget. | ||
| The project's deliverables have all been finished. The project came in ahead of schedule but on budget. |