Question: You are given the following earned value analysis information for a 10-month project at the end of the 7th month: SPI = 0.7, CPI =

You are given the following earned value analysis information for a 10-month project at the end of the 7th month: SPI = 0.7, CPI = 1.0. Which of the following choices best describes the information provided?

The project's deliverables have all been finished. The project came in on schedule but over budget.

The project is behind schedule but underspending its budget.

At that time the project was behind schedule and on budget.

The project's deliverables have all been finished. The project came in ahead of schedule but on budget.