Question: You are managing a 24 month project whose total budget is $150,000. At the end of month 18 you know that you should have spent

You are managing a 24 month project whose total
You are managing a 24 month project whose total budget is $150,000. At the end of month 18 you know that you should have spent a total of $60,000. You have actually spent $75,000. Based on this information, which of the following statements is true? The project will end up spending more than the total budget The project has a variance of -15000 none of the choices are correct The project is operating at 8 efficiency