Question: You are managing a project to launch a new website. The project consists of the following tasks, their durations, and their dependencies: Project Planning (
You are managing a project to launch a new website. The project consists of the following tasks, their durations, and their dependencies:
Project Planning A: days, no predecessors
Design Phase B: days, is a predecessor
Content Creation C: days, is predecessor
FrontEnd Development D: days, is a predecessor
BackEnd Development E: days, is a predecessor
Testing : days, and are both predecessors
Launch : days, is a predecessor
How long does this project take, in days? For example, if your answer is days, enter into the box.