Question: You are managing a project to launch a new website. The project consists of the following tasks, their durations, and their dependencies: Project Planning (

You are managing a project to launch a new website. The project consists of the following tasks, their durations, and their dependencies:
Project Planning (A): 5 days, no predecessors
Design Phase (B): 10 days, A is a predecessor
Content Creation (C): 8 days, A is predecessor
Front-End Development (D): 15 days, B is a predecessor
Back-End Development (E): 12 days, B is a predecessor
Testing (F):6 days, D and E are both predecessors
Launch (G):18 days, F is a predecessor
How long does this project take, in days? For example, if your answer is 100 days, enter 100 into the box.
 You are managing a project to launch a new website. The

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!