Question: Create a Microsoft Project MPP file titled youmame ICA Part 2mpp. Set the project start date to Monday, December 6, 2021. Create a Project Summary
Create a Microsoft Project MPP file titled youmame ICA Part 2mpp. Set the project start date to Monday, December 6, 2021. Create a Project Summary Task called 'Create Final Project Report' (as Task 0, per instructions in ICA 1) Add the following tasks, durations, dependencies, and assigned resources: (Note: Please verify Predecessor numbers and indenting when entering) ID Task Name Duratioa Predecessors Resource Names 1 Plan Final Report 2 Determine Report Structure 2 days Sally 3 Assign and schedule activities 1 day 2 John 4 Develop Report Template 3 days 3 Mary 5 Collect data 6 Research Data requirements 4 days 4 John, Mary 7 Analyze data collected 3 days 6 Mary. Sally 8 Develop conclusions and recommendations 3 days