Question: You are managing a project using the earned value technique for cost management. The project planned value (PV) is $200,000. The project earned value (EV)

  1. You are managing a project using the earned value technique for cost management. The project planned value (PV) is $200,000. The project earned value (EV) is $100,000. The actual value (AV) is $150,000.
    1. What is the schedule variance (SV) for the project?(5 points)
    2. What is the schedule performance index (SPI) for the project?(5 points)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!