Question: Youre managing a project using the earned value technique (EVT) for cost management. The project planned value (PV) is $200,000. The project earned value (EV)
You’re managing a project using the earned value technique (EVT) for cost management. The project planned value (PV) is $200,000. The project earned value (EV) is $100,000. The actual value (AV) is $150,000. What is the schedule performance index (SPI) for the project? ❍ A. 0.5 ❍ B. 1.5 ❍ C. 1.75 ❍ D. 2
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
