Question: You are managing a project using the earned value technique (EVT) for cost management. The project planned value (PV) is $200,000. The project earned value


You are managing a project using the earned value technique (EVT) for cost management. The project planned value (PV) is $200,000. The project earned value (EV) is $100,000. The actual value (AV) is $150,000. What is the schedule variance (SV) for the project?

A. 100,000 B. –100,000 C. 50,000 D. –50,000