Question: You are managing a second project that has the same time and cost specifications as those in Question 1, but which is 40% complete at
You are managing a second project that has the same time and cost specifications as those in Question 1, but which is 40% complete at the Status Date, when Actual Costs are $350,000.
Its specifications are below
Calculate the following quantities:
Using your results, apply the three (3) formula listed in calculation of the Estimate at Completion (EAC) of the project.
These formulas are as follows:
EAC=AC + (BAC EV)
EAC=BAC/CPI EAC= AC + [(BAC-EV) / (CPI x SPI)].
For each of these calculations, calculate the To-Complete
Performance Index (TCPI).
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
