Question: You are managing a second project that has the same time and cost specifications as those in Question 1, but which is 40% complete at

You are managing a second project that has the same time and cost specifications as those in Question 1, but which is 40% complete at the Status Date, when Actual Costs are $350,000.

Its specifications are below

Budgeted Actual Cost (BAC): $1,000,000.
Schedule time to complete: 12 months
Planned value (PV) $300,000
Actual cost (AC) $350,000
Percentage of work completed 25%

Calculate the following quantities:

Earned Value (EV)
Cost Variance (CV)
Schedule Variance (SV)
Cost performance index (CPI)
Schedule performance index (SPI)

Using your results, apply the three (3) formula listed in calculation of the Estimate at Completion (EAC) of the project.

These formulas are as follows:

EAC = AC +(BAC-EV)
EAC = BAC/CPI
EAC = AC + [(BAC-EV)/(CPI*SPI)]

EAC=AC + (BAC EV)

EAC=BAC/CPI EAC= AC + [(BAC-EV) / (CPI x SPI)].

For each of these calculations, calculate the To-Complete

Performance Index (TCPI).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!