Question: You are managing a second project that has the same time and cost specifications as those in Question 1, but which is 40% complete at
You are managing a second project that has the same time and cost specifications as those in Question 1, but which is 40% complete at the Status Date, when Actual Costs are $350,000.
Its specifications are below
- Budgeted Actual Cost (BAC): $1,000,000.
- Schedule time to complete: 12 months
- Planned value (PV) $300,000
- Actual cost (AC) $350,000
- Percentage of work completed 25%
Calculate the following quantities:
- Earned Value (EV)
- Cost Variance (CV)
- Schedule Variance (SV)
- Cost performance index (CPI)
- Schedule performance index (SPI)
Using your results, apply the three (3) formulae listed in calculation of the Estimate at Completion (EAC) of the project.
These formulae are as follows:
- EAC = AC +(BAC-EV)
- EAC = BAC/CPI
- EAC = AC + [(BAC-EV)/(CPI*SPI)]
EAC=AC + (BAC EV)
EAC=BAC/CPI EAC= AC + [(BAC-EV) / (CPI x SPI)].
For each of these calculations, calculate the To-Complete
Performance Index (TCPI).
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
