Question: You are managing a second project that has the same time and cost specifications as those in Question 1, but which is 40% complete at

You are managing a second project that has the same time and cost specifications as those in Question 1, but which is 40% complete at the Status Date, when Actual Costs are $350,000.

Its specifications are below

  • Budgeted Actual Cost (BAC): $1,000,000.
  • Schedule time to complete: 12 months
  • Planned value (PV) $300,000
  • Actual cost (AC) $350,000
  • Percentage of work completed 25%

Calculate the following quantities:

  • Earned Value (EV)
  • Cost Variance (CV)
  • Schedule Variance (SV)
  • Cost performance index (CPI)
  • Schedule performance index (SPI)

Using your results, apply the three (3) formulae listed in calculation of the Estimate at Completion (EAC) of the project.

These formulae are as follows:

  • EAC = AC +(BAC-EV)
  • EAC = BAC/CPI
  • EAC = AC + [(BAC-EV)/(CPI*SPI)]

EAC=AC + (BAC EV)

EAC=BAC/CPI EAC= AC + [(BAC-EV) / (CPI x SPI)].

For each of these calculations, calculate the To-Complete

Performance Index (TCPI).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!