Question: You are managing a software project with an initial budget estimate of 2 million USD. During interim cost and schedule performance analysis, you figured out
You are managing a software project with an initial budget estimate of million USD. During interim cost and schedule performance analysis, you figured out that: You should have spent $ till now based on your initial plans and manday of schedule activities You spent $ till now and completed mandays of schedule activities which should have cost $ based on your initial plans. You reestimated the budget required for the remaining work to be done as $
What is the CV and SV of the project respectively?
a CV$ and SV mandays
b CV $ and SV mandays
c CV$ and SV mandays
d CV $ and SV mandays