Question: You are managing a software project with an initial budget estimate of 2 million USD. During interim cost and schedule performance analysis, you figured out

You are managing a software project with an initial budget estimate of 2 million USD. During interim cost and schedule performance analysis, you figured out that: You should have spent $500,000 till now based on your initial plans and 1000 man/day of schedule activities You spent $600,000 till now and completed 1100 man/days of schedule activities which should have cost $450,000 based on your initial plans. You re-estimated the budget required for the remaining work to be done as $1,500,000.
What is the CV and SV of the project respectively?
a) CV=-$150.000 and SV=100 man/days
b) CV= $150.000 and SV=-100 man/days
c) CV=-$100.000 and SV=-100 man/days
d) CV= $100.000 and SV=100 man/days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!