Question: You are managing a software project with an initial budget estimate of 2 million USD. During interim cost and schedule performance analysis, you figured out
You are managing a software project with an initial budget
estimate of million USD. During interim cost and schedule
performance analysis, you figured out that:
You should have spent $ till now based on your initial
plans and manday of schedule activities
You spent $ till now and completed mandays of
schedule activities which should have cost
$ based on your initial plans.
You reestimated the budget required for the remaining work to
be done as $