Question: You are managing a software project with an initial budget estimate of 2 million USD. During interim cost and schedule performance analysis, you figured out

You are managing a software project with an initial budget
estimate of 2 million USD. During interim cost and schedule
performance analysis, you figured out that:
You should have spent $500,000 till now based on your initial
plans and 1000 man/day of schedule activities
You spent $600,000 till now and completed 1100 man/days of
schedule activities which should have cost
$450,000 based on your initial plans.
You re-estimated the budget required for the remaining work to
be done as $1,500,000.