Question: You are managing software application project which is to be completed at a budget of RM120,000. Gamed value analysis shows that so far you have

You are managing software application project

You are managing software application project which is to be completed at a budget of RM120,000. Gamed value analysis shows that so far you have completed 30% of the work and spent R1460,000. You expect the cost performance to remain unchanged. Perform the following IV V VI. Frned value (EV) Cosi performance index (CPI) Estimate at completion (EAC) Estimate to complete (ETC) To Complete Performance Index (TCPI) What can you deduce about the state of the project from the above calculations? and How EV analysis help project manager and management? (20 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!