Question: You are managing software application project which is to be completed at a budget of RM120,000. Gamed value analysis shows that so far you have

You are managing software application project which is to be completed at a budget of RM120,000. Gamed value analysis shows that so far you have completed 30% of the work and spent R1460,000. You expect the cost performance to remain unchanged. Perform the following IV V VI. Frned value (EV) Cosi performance index (CPI) Estimate at completion (EAC) Estimate to complete (ETC) To Complete Performance Index (TCPI) What can you deduce about the state of the project from the above calculations? and How EV analysis help project manager and management? (20 marks)