Question: You are on a project team to create a website with a project budget of $400,000. There are 8 planned iterations to deliver 240 initial

You are on a project team to create a website with a project budget of $400,000. There are 8 planned iterations to deliver 240 initial story points (the backlog) with each iteration expected to deliver 30 story points. Fill in the follow table below to determine project status

At the end of iteration 4 there is a project review. What is the Cost Variance, Schedule Variance, CPI, and SPI at this point in the project? Create a burn down chart which shows the planned burndown of story points along with the actual completion for each iteration. Given the numbers you have calculated in the questions above as well as your burn down charts, is the project doing well or is it in trouble? How many iterations will be required to finish the project? What would you expect the budget overage to be?

Iteration Points in Backlog Points Completed Points Added Remaining Backlog Earned Value to Date Planned Actual Value Cost fo 

Iteration 2 3 4 5 6 7 8 Points in Backlog 240 210 185 Points: Points Completed Added 30 25 30 30 20 25 35 40 0 0 15 0 10 20 0 0 Remaining Backlog 210 185 170 Planned Value (Cumulative) $50K $100K $150K Actual Cost for the Iteration and Cumulative for the Project $55K $55K $50K $105K $60K $50K $55K $30K $45K $50K Earned Value to Date .125 or $50K 23 or $91.6K

Step by Step Solution

3.40 Rating (156 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Question Itera Points in Points Points tion Backlog Completed Added 1 240 2 21... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (2 attachments)

PDF file Icon

636a609fab2b2_213822.pdf

180 KBs PDF File

Word file Icon

636a609fab2b2_213822.docx

120 KBs Word File

Students Have Also Explored These Related General Management Questions!