Question: Daily demand for an item is shown here. Assume a holding cost of $0.50 per unit per day, a setup cost of $100 per setup,

Daily demand for an item is shown here. Assume a holding cost of $0.50 per unit per day, a setup cost of $100 per setup, a lead time of one day and 70 units on hand. Determine when a work order should be released for the item and the size of the order using the L4L, EOQ, and POQ lot sizing techniques. Which technique produces the lowest totalcost?

Daily demand for an item is shown here. Assume a

1 2 3 4 5 6 7 8 9 10 Gross Requirement 50 30 25 35 40 50 35 45 70 75 rio

Step by Step Solution

3.40 Rating (166 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

10000 Exact Rounded 050 13491 135 4550 296 3 Item X LLC 1 Period Lot Size L4L 1 LT 1 1 2 3 4 5 6 7 8 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Excel file Icon

184_6075669f968eb_143306.xlsx

300 KBs Excel File

Students Have Also Explored These Related Management Leadership Questions!