Question: You are performing an earned value analysis on your 25-week project. The project was scheduled to be 60 percent complete at this time. You have
You are performing an earned value analysis on your 25-week project. The project was scheduled to be 60 percent complete at this time. You have completed 16 of the 30 deliverables (all of equal value). You have spent $25,000 of your total original budget of $55,000. The first deliverable took twice as long and cost twice as much as was planned and budgeted.
Calculate the following:
Budget at completion
Actual cost
Planned value
Earned value
Cost variance
Cost performance index
Schedule variance
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
