Question: You are preparing a Class 5 estimate, what will be the typical maturity level of the project definitions deliverables (expressed as % of complete definition)?
You are preparing a Class 5 estimate, what will be the typical maturity level of the project definitions deliverables (expressed as % of complete definition)?
| a. | 1%-5% | |
| b. | 10-40% | |
| c. | 2%-6% | |
| d. | 0%-2% | |
| e. | 2-3% |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts