Question: 10. You are preparing a Class 5 estimate, what will be the typical maturity level of the project definitions deliverables (expressed as % of complete

10.

You are preparing a Class 5 estimate, what will be the typical maturity level of the project definitions deliverables (expressed as % of complete definition)?

a.

1%-5%

b.

10-40%

c.

2%-6%

d.

0%-2%

e.

2-3%

11.

You are preparing a Class 5 estimate, you have obtained an equipment quote of R80 000. The Lang Factor is 4.15 for this type of plant. What is the estimated project cost?

a.

R207 900

b.

R256 642

c.

R201 910

d.

R332 000

e.

R198 000

12.

What is another term for capacity Factor Method?

a.

Parametric Method

b.

Scale of Operations Method

c.

End-Product Unit Method

d.

Deterministic Method

e.

Bottom-up Method

PLEASE ANSWER TIMEOUSLY

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!