Question: 10. You are preparing a Class 5 estimate, what will be the typical maturity level of the project definitions deliverables (expressed as % of complete
10.
You are preparing a Class 5 estimate, what will be the typical maturity level of the project definitions deliverables (expressed as % of complete definition)?
| a. | 1%-5% | |
| b. | 10-40% | |
| c. | 2%-6% | |
| d. | 0%-2% | |
| e. | 2-3% |
11.
You are preparing a Class 5 estimate, you have obtained an equipment quote of R80 000. The Lang Factor is 4.15 for this type of plant. What is the estimated project cost?
| a. | R207 900 | |
| b. | R256 642 | |
| c. | R201 910 | |
| d. | R332 000 | |
| e. | R198 000 |
12.
What is another term for capacity Factor Method?
| a. | Parametric Method | |
| b. | Scale of Operations Method | |
| c. | End-Product Unit Method | |
| d. | Deterministic Method | |
| e. | Bottom-up Method |