Question: Elena Wilhelm is responsible for developing a comprehensive sales training program for her organization. The following table describes the relationships between the activities that need
.png)
Assume that the actual duration of each activity follows a discrete uniform distribution between the minimum and maximum times shown for that activity. Use simulation to determine the probability that the project will be finished in less than 49 days. Round off each activity time to the nearest whole number.
DAYS IMMEDIATE ACTIVITY MINIMUM MAXIMUM PREDECESSORS 13 A, B 12 12 F, H G, I 10
Step by Step Solution
3.54 Rating (161 Votes )
There are 3 Steps involved in it
tr msoheightsourceauto col msowidthsourceauto br msodataplacementsamecell style0 msonumberformatGeneral textaligngeneral verticalalignbottom whitespacenowrap msorotate0 msobackgroundsourceauto msopatt... View full answer