Question: You are the lead industrial engineer working at Maxis Machine Shop. Maxis needs to complete the set of jobs with processing times given below. Maxis
You are the lead industrial engineer working at Maxis Machine Shop. Maxis needs to complete the set of jobs with processing times given below. Maxis has three machines that can process each of the jobs and a job only has to be processed on any one of the machines. The first machine requires the time value given in the table, the second machine requires two times the time value given in the table, and the third machine requires three times the time value given in the table. (For example, job A requires 12 time units on machine 1, 24 time units on machine 2, and 36 time units on machine 3). How would you assign the jobs to the machines if the objective is to minimize the makespan?
Job A B C D E F G H I J
Time 12 8 6 3 10 7 6 10 5 4
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts