Question: You are the project manager for a new project and have figured out the following dependencies; 1. Activity 1 can start immediately and has an
You are the project manager for a new project and have figured out the following dependencies;
1. Activity 1 can start immediately and has an estimated duration of 3 weeks
2. Activity 2 can start after Activity 1 is completed and has an estimated duration of 3 weeks
3. Activity 3 can start after Activity 1 is completed and has an estimated duration of 6 weeks
4. Activity 4 can start after Activity 2 is completed and has an estimated duration of 8 weeks
5. Activity 5 can start after Activity 4 is completed and activity 3 is completed. This activity takes has an estimated duration of 6 weeks
Question
What is the float of activity 3?