Question: You are the project manager for a new project and have figured out the following dependencies; 1. Activity 1 can start immediately and has an

You are the project manager for a new project and have figured out the following dependencies;

1.     Activity 1 can start immediately and has an estimated duration of 3 weeks

2.     Activity 2 can start after Activity 1 is completed and has an estimated duration of 3 weeks

3.     Activity 3 can start after Activity 1 is completed and has an estimated duration of 6 weeks

4.     Activity 4 can start after Activity 2 is completed and has an estimated duration of 8 weeks

5.     Activity 5 can start after Activity 4 is completed and activity 3 is completed. This activity takes has an estimated duration of 6 weeks

Question

What is the float of activity 3?

Step by Step Solution

3.55 Rating (169 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!