Question: You are the project manager for a software development project. The project sponsor has requested a budget estimate for the project. You have gathered all
You are the project manager for a software development project. The project sponsor has requested a budget estimate for the project. You have gathered all the necessary cost information from the project team and vendors. Which of the following processes will you primarily use to come up with the project budget?
a Determine Budget
b Monitor and Control the Cost
c Cost Management Plan
d Estimate Cost