Question: You are the project manager for an ongoing project. At the start of the project, you summarized the durations and precedents for each activity using

 You are the project manager for an ongoing project. At the

You are the project manager for an ongoing project. At the start of the project, you summarized the durations and precedents for each activity using the following Precedents Table. The project has a Required Completion Time of 18 days. As of today, 4 of the activities (A, B, F and H) have been completed. The completion dates for these 4 activities have been added to the table: Update your project schedule using the Actual Finish Times for the activities that have been completed. Calculate the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF), Total Slack (TS) and Free Slack (FS) for each activity in your updated schedule. What is (are) the critical path(s) for the updated project schedule

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!