Question: You are the Project Manager for the modification and production component of a plan re-engineering project. The contract has two years of performance and you

You are the Project Manager for the modification and production component of a plan re-engineering project. The contract has two years of performance and you are halfway through with the contract. Your cumulative to- date Earned Value (EV) is $500,000 and the cumulative to-date Actual Cost (AC) is $600,000. Your Budget at Completion (BAC) is $1,000,000. You want to calculate an Estimate at Completion (EAC) using your Cost Performance Index (CPI) since the expectation is current performance will be typical of future performance. For this project what is the Estimate at Completion (EAC)?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!