Question: You are the Project Manager for the modification and production component of a plan re-engineering project. The contract has two years of performance and you
You are the Project Manager for the modification and production component of a plan re-engineering project. The contract has two years of performance and you are halfway through with the contract. Your cumulative to- date Earned Value (EV) is $500,000 and the cumulative to-date Actual Cost (AC) is $600,000. Your Budget at Completion (BAC) is $1,000,000. You want to calculate an Estimate at Completion (EAC) using your Cost Performance Index (CPI) since the expectation is current performance will be typical of future performance. For this project what is the Estimate at Completion (EAC)?