Question: You are the project manager of a large, complex, multi - year project. In the past, you have planned out all the details of the

You are the project manager of a large, complex, multi-year project. In the past,
you have planned out all the details of the activities early in the project . For your
current project you are more likely to do progressive elaboration through:
Group of answer choices
Rolling Wave Planning
Templates
WBS
Scope Management