Question: You are using a burnup chart to visually provide information about project progress to the agile team. Which of the following are true regarding a
You are using a burnup chart to visually provide information about project progress to the agile team. Which of the following are true regarding a burnup chart?
Question options:
This is a type of capacity measure.
This shows the completed work for the iteration or project.
Accuracy depends on the accuracy of the team's estimates.
It can't tell you if you are working on the right things.
A B D
A B C D
A C D