Question: You are working on a project to host an important event for your company. Task A has a duration of 2 days, and it s
You are working on a project to host an important event for your company. Task A has a duration of days, and its on the Critical Path. The resource assigned is an interior decorator. The interior decorator asks you if they can do the task days late, instead of the assigned date. You cannot change the event date. Which decision from the options below will allow you to keep your original event date?
Group of answer choices
Create a new baseline for the project
Hire another interior decorator who can do the work on the original date
Accept the request of the interior decorator
Ask the interior decorator to do the task days late instead