Question: You are working on a project with a defined scope and schedule . The work that needs to be done requires a special skill set

You are working on a project with a defined scope and schedule . The work that needs to be done requires a special skill set that your team does not possess Stakeholders are adamant about the project going live on time . Given the schedule constraints , training is unlikely to happen . What should you do ? A Request that the project be halted until the team can be trained . B Train the team on the special skill set and expand the schedule to account for this Obtain resources that have the required skills . D Escalate to the project sponsor